BNSF Sends Seven Track Gangs to the Southwest


WEBWIRE

Beginning Jan. 8, 2009, BNSF Railway Company will dispatch seven maintenance crews to replace rail and ties between Clovis and Jarales, N.M; Baca, N.M. and Winslow, Ariz.; and Crookton and Griffith, Ariz.

Two hundred and fifty BNSF employees and contractors will work until April replacing approximately 150,000 ties and almost 150 track miles of rail. The total cost of these three projects is more than $30 million. Crews will utilize equipment such as cranes, welders and ballast tampers to replace rail at an estimated rate of one mile a day. Materials replaced on the rail line will be reused or recycled in keeping with BNSF’s environmental stewardship policies.

To allow the BNSF crew time to replace the rail, sections of track will be closed periodically during rail and tie replacement until the work is complete.



WebWireID83826





This news content was configured by WebWire editorial staff. Linking is permitted.

News Release Distribution and Press Release Distribution Services Provided by WebWire.